Skip to content

Construction Updates

Updated May 15, 2025

Construction for the new hospital and parking structure is moving forward at a rapid pace. In fact, the parking structure is now 28% complete, with an estimated completion date of May 2026!

Read below to learn about the construction progress. To watch a new aerial view of the project, click here to watch the drone video.

Hospital & Energy Center Updates

5/1/25 – Start of Rock Layer for Foundation Pad (see image below)

5/8/25 – Area 1 rock pad 95% complete and west truck ramp removed (see image below)

5/8/25 - Area 1 rock pad 95% complete and west truck ramp removed (see image below)

5/12/25 – Pouring mud slab (see image below)

5/15/25 – Installation of waterproofing (see image below)

Parking Structure is now 28% Complete

Rebar installation in pile caps at north end of hospital (see image below)

Parking Structure Updates

5/16/25 – Level 2 slab poured, beam forms for Level 3 being placed (see image below)

Parking Structure is now 28% Complete

Parking Structure is now 28% Complete

Upcoming Work

Upcoming Work in the next 60 Days for Hospital/Energy Center Project:

  • Pour Pile Caps
  • Waterproofing below Mat Foundation
  • Pour Protection Slab
  • Form and Pour Hospital Mat Foundation
  • Form and Pour Perimeter Concrete Walls
  • Continue Underground Utilities
  • Mud Slab & Waterproofing for Fuel Tanks
  • Excavation & Mud Slab for Grease Tank & Plumbing Trenches

Upcoming Work in the next 60 Days for Parking Structure Project:

  • Complete Level 2 Deck
  • Level 3 Ramp and Deck
  • Perimeter Crashwalls
  • Prep for PG&E Transformer and Switch
Back To Top