Construction Updates
Updated May 15, 2025
Construction for the new hospital and parking structure is moving forward at a rapid pace. In fact, the parking structure is now 28% complete, with an estimated completion date of May 2026!
Read below to learn about the construction progress. To watch a new aerial view of the project, click here to watch the drone video.
Hospital & Energy Center Updates
5/1/25 – Start of Rock Layer for Foundation Pad (see image below)

5/8/25 – Area 1 rock pad 95% complete and west truck ramp removed (see image below)

5/12/25 – Pouring mud slab (see image below)

5/15/25 – Installation of waterproofing (see image below)

Parking Structure is now 28% Complete

Parking Structure Updates
5/16/25 – Level 2 slab poured, beam forms for Level 3 being placed (see image below)

Parking Structure is now 28% Complete

Upcoming Work
Upcoming Work in the next 60 Days for Hospital/Energy Center Project:
- Pour Pile Caps
- Waterproofing below Mat Foundation
- Pour Protection Slab
- Form and Pour Hospital Mat Foundation
- Form and Pour Perimeter Concrete Walls
- Continue Underground Utilities
- Mud Slab & Waterproofing for Fuel Tanks
- Excavation & Mud Slab for Grease Tank & Plumbing Trenches
Upcoming Work in the next 60 Days for Parking Structure Project:
- Complete Level 2 Deck
- Level 3 Ramp and Deck
- Perimeter Crashwalls
- Prep for PG&E Transformer and Switch